BuildingRoom #Room Capacity

Apprx. Social

Distance Capacity

Status

Projected Completion

(dates may change)

Anderson Bio Lab1305214 Installation to begin week of 8/10/20208/14/2020
Anderson Bio Lab13112023 Installation to begin week of 8/10/20208/14/2020
Anderson Hall117599 Installation to begin week of 8/10/20208/14/2020
Baker Hall1023510Substantially completed
Awaiting items for full completion
8/14/2020
Baker Hall1164310Substantially completed
Awaiting items for full completion
8/14/2020
BioScience Research C2826620Substantially completed
Awaiting items for full completion
8/7/2020
BioScience Research C2845015Substantially completed
Awaiting items for full completion
8/14/2020
Brockman10114430In Process8/14/2020
Brockman1033012 Installation to begin week of 8/10/20208/14/2020
Dell Butcher1808722 Installation to begin week of 8/10/20208/14/2020
Duncan College1136024Substantially completed
Awaiting items for full completion
8/14/2020
Duncan Hall10424614Substantially completed
Awaiting items for full completion
8/14/2020
Duncan Hall10464613Substantially completed
Awaiting items for full completion
8/14/2020
Duncan Hall10647320Completed 
Duncan Hall10707320Substantially completed
Awaiting items for full completion
8/14/2020
Duncan Hall10753511Substantially completed
Awaiting items for full completion
8/14/2020
Duncan Hall1020 (Symonds II)6625 Installation to begin week of 8/10/20208/12/2020
Herring10019742Completed 
Herman Brown Hall2274616Installation in Process8/14/2020
Herman Brown Hall427277Installation in Process8/14/2020
Herzstein21012515Substantially completed
Awaiting items for full completion
8/14/2020
Herzstein21212315Substantially completed
Awaiting items for full completion
8/14/2020
HerzsteinAmp30040 Installation to begin week of 8/10/20208/14/2020
Humanities1177021Completed 
Humanities118247 Installation to begin week of 8/10/20208/14/2020
Humanities119359Substantially completed
Awaiting items for full completion
8/14/2020
Humanities

226

246 Installation to begin week of 8/10/20208/14/2020
Humanities227249 Installation to begin week of 8/10/20208/14/2020
Humanities327247 Installation to begin week of 8/10/20208/14/2020
Humanities3283010Substantially completed
Awaiting items for full completion
8/7/2020
Keck10026548In Process8/14/2020
Keck1013010In Process8/14/2020
Keck1026916 Installation to begin week of 8/10/20208/14/2020
Keith Weiss Geology1006815Substantially completed
Awaiting items for full completion
8/14/2020
Keith Weiss Geology128189 Installation to begin week of 8/10/20208/14/2020
Kraft Hall1054516Substantially completed
Awaiting items for full completion
8/14/2020
Kraft Hall1108624Substantially completed
Awaiting items for full completion
8/14/2020
Kraft Hall1254816Completed 
Mechanical Engineering1284814 Installation to begin week of 8/10/20208/14/2020
Rayzor106288Substantially completed
Awaiting items for full completion
8/14/2020
Rayzor1132011Substantially completed
Awaiting items for full completion
8/14/2020
Rayzor1196417Substantially completed
Awaiting items for full completion
8/7/2020
Rayzor1233912Substantially completed
Awaiting items for full completion
8/7/2020
Rayzor205205Substantially completed8/7/2020
Ryon1022010 Installation to begin week of 8/10/20208/12/2020
Ryon2017814Substantially completed
Awaiting items for full completion
8/7/2020
Sewall30116829Substantially completed
Awaiting items for full completion
8/14/2020
Sewall3034511Completed 
Sewall3054511Substantially completed
Awaiting items for full completion

8/7/2020

Sewall3074511Substantially completed
Awaiting items for full completion
8/14/2020
Sewall3098215Substantially completed
Awaiting items for full completion
8/14/2020
Sewall Hall207 (Symonds I)3618 Installation to begin week of 8/10/20208/12/2020
Space Science1065414 Installation to begin week of 8/10/20208/14/2020