DepartmentBuildingRoom #Status

Projected Completion

(dates may change)

ArchitectureAnderson HallStudio Rooms (13)Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson HallJury RoomAwaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson HallFarrish GalleryAwaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall148Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall153Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall154Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall210Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall217Awaiting Building AC Project
to complete (8/12)
8/1921/2020
ArchitectureAnderson Hall230Awaiting Building AC Project
to complete (8/12)
8/1921/2020
MusicAlice Pratt Brown1401 In progress8/7/2020
MusicAlice Pratt Brown1402 In progress8/7/2020
MusicAlice Pratt Brown1403 In progress8/7/2020
MusicAlice Pratt Brown1404 In progress8/7/2020
MusicAlice Pratt Brown1131 In progress8/7/2020
MusicAlice Pratt Brown1133 In progress8/7/2020
MusicAlice Pratt Brown1705 In progress8/7/2020
HumanitiesHamman HallConcourse Installation to begin week of 8/17/20208/1921/2020
HumanitiesHamman HallAuditorium Installation to begin week of 8/17/20208/1921/2020
HumanitiesHamman Hall103 Installation to begin week of 8/17/20208/1921/2020
HumanitiesHamman Hall106 Installation to begin week of 8/17/20208/1921/2020
HumanitiesSewall Hall405 Installation to begin week of 8/17/20208/1921/2020
HumanitiesSewall Hall413 Installation to begin week of 8/17/20208/1921/2020
HumanitiesSewall Hall415 Installation to begin week of 8/17/20208/1921/2020
HumanitiesMedia CenterTheater Installation to begin week of 8/17/20208/1921/2020
EngineeringBRC230 

Equipment/Accessories to be delivered by 8/12/2020

Installation to begin week of 8/17/2020

Partial 8/12/2020

Remaining 8/1921/2020

EngineeringMechanical Eng. Building117A Equipment/Accessories to be delivered by 8/12/20208/12/2020
EngineeringMechanical Eng. Building117B Equipment/Accessories to be delivered by 8/12/20208/12/2020
EngineeringRyon LabOpen Bay Equipment/Accessories to be delivered by 8/12/20208/12/2020
EngineeringRyon LabB02 Equipment/Accessories to be delivered by 8/12/20208/12/2020
EngineeringKeck Hall108-113 Equipment/Accessories to be delivered by 8/12/20208/12/2020
EngineeringOEDK114 Installation to begin week of 8/17/20208/1921/2020
EngineeringOEDKLab Installation to begin week of 8/17/20208/1921/2020
EngineeringOEDKOpen Spaces

Equipment/Accessories to be delivered by 8/12/2020

Installation to begin week of 8/17/2020

 

Partial 8/12/2020

Remaining 8/1921/2020

Natural SciencesAnderson Biology123 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesAnderson Biology126 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesAnderson Biology127 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesAnderson Biology128 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesAnderson Biology129 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesAnderson Biology305 Equipment/Accessories to be delivered by 8/12/20208/12/2020
Natural SciencesTudorS97 Equipment/Accessories to be delivered by 8/12/20208/12/2020