8/7/2020 to be by 8/12/2020Installation to begin week of 8/17/2020
to be to be to be to be to be to be to be to be to be to be
DepartmentBuildingRoom #Status

Projected Completion

(dates may change)

ArchitectureAnderson HallStudio Rooms (13)Awaiting Building AC Project
to complete (8/12)
Completed 8/24/2020
ArchitectureAnderson HallJury RoomAwaiting Building AC Project
to complete (8/12)
8/24/2020Completed 
ArchitectureAnderson HallFarrish GalleryAwaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
ArchitectureAnderson Hall148Awaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
ArchitectureAnderson Hall153Awaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
ArchitectureAnderson Hall154Awaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
ArchitectureAnderson Hall210Awaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
ArchitectureAnderson Hall217Awaiting Building AC Project
to complete (8/12)
Completed 8/21/2020
ArchitectureAnderson Hall230Awaiting Building AC Project
to complete (8/12)
8/21/2020Completed 
MusicAlice Pratt Brown1401In progressCompleted 8/7/2020
MusicAlice Pratt Brown1402In progressCompleted 8/7/2020
MusicAlice Pratt Brown1403In progressCompleted 8/7/2020
MusicAlice Pratt Brown1404In progressCompleted 8/7/2020
MusicAlice Pratt Brown1131In progressCompleted 8/7/2020
MusicAlice Pratt Brown1133In progressCompleted 8/7/2020
MusicAlice Pratt Brown1705In progressCompleted 
MusicBHO/RUMPAC221Completed
HumanitiesHamman HallConcourseInstallation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesHamman HallAuditoriumInstallation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesHamman Hall103Installation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesHamman Hall106Installation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesSewall Hall405Installation to begin week of 8/17/2020Completed 8/21/2020
HumanitiesSewall Hall413Installation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesSewall Hall415Installation to begin week of 8/17/2020Completed 8/24/2020
HumanitiesMedia CenterTheaterInstallation to begin week of 8/17/2020Completed 8/21/2020
EngineeringBRC230

Equipment/Accessories

delivered

Room Completed

 

Partial 8/12/2020

Remaining 8/21/2020

EngineeringMechanical Eng. Building117AEquipment/Accessories delivered  by 8/12/20208/12/2020
EngineeringMechanical Eng. Building117BEquipment/Accessories delivered  by 8/12/20208/12/2020
EngineeringRyon LabOpen BayEquipment/Accessories delivered  by 8/12/20208/12/2020
EngineeringRyon LabB02Equipment/Accessories delivered  by 8/12/20208/12/2020
EngineeringKeck Hall108-113Equipment/Accessories to be delivered by 8/12/2020Completed 8/12/2020
EngineeringOEDK114Installation to begin week of 8/17/2020Completed 8/21/2020
EngineeringOEDKLabInstallation to begin week of 8/17/2020Completed 8/24/2020
EngineeringOEDKOpen Spaces

Completed

 

 

EngineeringOEDKB02Completed 

Equipment/Accessories to be delivered by 8/12/2020

Installation to begin week of 8/17/2020

Partial 8/12/2020

Remaining 8/24/2020
Natural SciencesAnderson Biology123Equipment/Accessories delivered  by 8/12/20208/12/2020
Natural SciencesAnderson Biology126Equipment/Accessories delivered  by 8/12/20208/12/2020
Natural SciencesAnderson Biology127Equipment/Accessories delivered  by 8/12/20208/12/2020
Natural SciencesAnderson Biology128Equipment/Accessories delivered  by 8/12/20208/12/2020
Natural SciencesAnderson Biology129Equipment/Accessories delivered  by 8/12/20208/12/2020
Natural SciencesAnderson Biology305Equipment/Accessories to be delivered by 8/12/2020Completed 8/12/2020
Natural SciencesTudorS97Equipment/Accessories delivered  by 8/12/20208/12/2020