tunePlease see this page for some photos of the installation progress in selected rooms.
The following OTR rooms are targeted for additional technology to enable dual teaching:
Building | Room # | Room Capacity | Apprx. Social Distance Capacity | Status | Projected Completion (dates may change) | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Anderson Bio Lab | 130 | 52 | 1413 | Completed | 8/14/2020 | |||||||
Anderson Bio Lab | 131 | 120 | 2317 | Completed | 8/14/2020 | |||||||
Anderson Hall | 117 | 59 | 89 | Completed | 8/14/2020 | Baker Hall | 102 | 35 | 10 | Substantially completed Awaiting items for full completion | 8/14/2020 | |
Baker Hall | 116 | 43 | 10 | Substantially completed Awaiting items for full completion | 8/14/2020 | |||||||
BioScience Research C | 282 | 66 | 1620 | Substantially completed Awaiting items for full completion | Completed | 8/7/2020 | ||||||
BioScience Research C | 284 | 50 | 1215 | Substantially completed Awaiting items for full completion | Completed | 8/14/2020 | ||||||
Brockman | 101 | 144 | 36 | Substantial completion 7/31 Awaiting items for full completion | 8/14/2020 | 30 | Completed | |||||
Brockman | 103 | 30 | 7 | Substantial completion 7/31 Awaiting items for full completion | 8/14/2020 | 12 | Completed | |||||
Dell Butcher | 180 | 87 | 2212 | Completed | 8/14/2020 | |||||||
Duncan College | 113 | 60 | 24 | Completed *(Awaiting replacement of one rear monitor.) | 8/14/2020 | |||||||
Duncan Hall | 1042 | 46 | 1114 | Completed | 8/14/2020 | |||||||
Duncan Hall | 1046 | 46 | 1311 | Completed | 8/14/2020 | |||||||
Duncan Hall | 1064 | 73 | 1420 | Substantially completed Awaiting items for full completion | Completed | 8/3/2020 | ||||||
Duncan Hall | 1070 | 73 | 1420 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Duncan Hall | 1075 | 35 | 118 | Completed | 8/14/2020 | |||||||
Duncan Hall | 1020 (Symonds II) | 66 | 2522 | Completed | 8/12/2020 | |||||||
Herring | 100 | 197 | 28 | Substantially completed Awaiting items for full completion | 42 | Completed | ||||||
Herman Brown Hall | 227 | 46 | 16 | Completed | ||||||||
Herman Brown Hall | 427 | 27 | 7 | Completed | 8/3/2020 | |||||||
Herzstein | 210 | 125 | 1815 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Herzstein | 212 | 123 | 1815 | Substantially completed Awaiting items for full completion | Completed | 8/14/2020 | ||||||
Herzstein | Amp | 300 | 4043 | Completed | 8/14/2020 | |||||||
Humanities | 117 | 70 | 21 | Completed | ||||||||
Humanities | 118 | 24 | 7 | Completed | 17 | Substantially completed Awaiting items for full completion | 8/3/2020 | |||||
Humanities | 119 | 35 | 9 | Completed | ||||||||
Humanities | 226 | 24 | 6 | Completed | ||||||||
Humanities | 227 | 24 | 9 | Completed | ||||||||
Humanities | 327 | 24 | 7 | Completed | 8 | Substantially completed Awaiting items for full completion | 8/14/2020 | |||||
Humanities | 328 | 30 | 710 | Substantially completed Awaiting items for full completion | 8/7/2020 | Completed | ||||||
Keck | 100 | 26538 | 48 | Completed | 8/14/2020 | |||||||
Keck | 101 | 30 | 107 | Completed | 8/14/2020 | |||||||
Keck | 102 | 6910 | 16 | Completed | 8/14/2020 | |||||||
Keith Weiss Geology | 100 | 68 | 1015 | Substantially completed Awaiting items for full completion | Completed | 8/14/2020 | ||||||
Keith Weiss Geology | 128 | 18 | 9 | Completed | 8/14/2020 | |||||||
Kraft Hall | 105 | 45 | 1116 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Kraft Hall | 110 | 86 | 1724 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Kraft Hall | 125 | 48 | 1216 | Substantially completed Awaiting items for full completion | Completed | 8/3/2020 | ||||||
Mechanical Engineering | 128 | 4812 | 14 | Completed | 8/14/2020 | |||||||
Rayzor | 106 | 28 | 8 | Substantially completed Awaiting items for full completion | Completed | 8/14/2020 | ||||||
Rayzor | 113 | 20 | 11 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Rayzor | 119 | 64 | 1617 | Substantially completed Awaiting items for full completion | 8/7/2020 | Completed | ||||||
Rayzor | 123 | 39 | 12 | Completed | ||||||||
Rayzor | 205 | 20 | 5 | Completed | 9 | Substantially completed Awaiting items for full completion | 8/7/2020 | |||||
Ryon | 102 | 20 | 10 | Completed | 8/12/2020 | |||||||
Ryon | 201 | 78 | 1014 | Substantially completed Awaiting items for full completion | 8/7/2020 | Completed | ||||||
Sewall | 301 | 168 | 2924 | Completed | 8/14/2020 | |||||||
Sewall | 303 | 45 | 911 | Substantially completed Awaiting items for full completion | Completed | 8/3/2020 | ||||||
Sewall | 305 | 45 | 911 | Substantially completed Awaiting items for full completion | Completed | 8/7/2020 | ||||||
Sewall | 307 | 45 | 911 | Substantially completed Awaiting items for full completion | 8/14/2020 | Completed | ||||||
Sewall | 309 | 8212 | 15 | Completed | 8/14/2020 | |||||||
Sewall Hall | 207 (Symonds I) | 36 | 18 | Completed | 8/12/2020 | |||||||
Space Science | 106 | 54 | 1413 | Completed | 8/14/2020 |