Partial Installation in progress
Waiting on Customer
DepartmentBuildingRoom #Status

Projected Completion

(dates may change)

ArchitectureAnderson HallStudio Rooms (13)Installation in progressCompleted 8/24/2020
ArchitectureAnderson HallJury RoomInstallation in progressCompleted 8/24/2020
ArchitectureAnderson HallFarrish GalleryInstallation in progressCompleted 8/21/2020
ArchitectureAnderson Hall148Installation in progressCompleted 8/21/2020
ArchitectureAnderson Hall153Installation in progressCompleted 8/21/2020
ArchitectureAnderson Hall154Installation in progressCompleted 8/21/2020
ArchitectureAnderson Hall210Installation in progressCompleted 8/21/2020
ArchitectureAnderson Hall217Installation in progressCompleted 8/21/2020
ArchitectureAnderson Hall230Installation in progressCompleted 8/21/2020
MusicAlice Pratt Brown1401Completed 
MusicAlice Pratt Brown1402Completed 
MusicAlice Pratt Brown1403Completed 
MusicAlice Pratt Brown1404Completed 
MusicAlice Pratt Brown1131Completed 
MusicAlice Pratt Brown1133Completed 
MusicAlice Pratt Brown1705Completed 
MusicBHO/RUMPAC221Installation to begin week of 8/24/20208/28/2020 *Workaround will be in place
Completed
HumanitiesHamman HallConcourseInstallation in progressCompleted 8/24/2020
HumanitiesHamman HallAuditoriumInstallation in progressCompleted 8/24/2020
HumanitiesHamman Hall103Installation in progressCompleted 8/24/2020
HumanitiesHamman Hall106Installation in progressCompleted 8/24/2020
HumanitiesSewall Hall405Installation in progressCompleted 8/21/2020
HumanitiesSewall Hall413Installation in progressCompleted 8/24/2020
HumanitiesSewall Hall415Installation in progressCompleted 8/24/2020
HumanitiesMedia CenterTheaterCompleted 
EngineeringBRC230

Equipment/Accessories delivered

Room Completed

Remaining 8/21/2020 

EngineeringMechanical Eng. Building117AEquipment/Accessories delivered 
EngineeringMechanical Eng. Building117BEquipment/Accessories delivered 
EngineeringRyon LabOpen BayEquipment/Accessories delivered 
EngineeringRyon LabB02Equipment/Accessories delivered 
EngineeringKeck Hall108-113Completed 
EngineeringOEDK114Completed 
EngineeringOEDKLabInstallation in progressCompleted 8/24/2020
EngineeringOEDKOpen Spaces

Completed

 

 

EngineeringOEDKB02Completed 

Waiting on Customer

Carts to arrive 9/18

 

9/18 *Not needed before then
Natural SciencesAnderson Biology123Equipment/Accessories delivered 
Natural SciencesAnderson Biology126Equipment/Accessories delivered 
Natural SciencesAnderson Biology127Equipment/Accessories delivered 
Natural SciencesAnderson Biology128Equipment/Accessories delivered 
Natural SciencesAnderson Biology129Equipment/Accessories delivered 
Natural SciencesAnderson Biology305Installation in progressCompleted 8/24/2020
Natural SciencesTudorS97Equipment/Accessories delivered