8/28/2020 *Workaround will be in placePartial In final testing
Waiting on Customer

 

9/18 *Not needed before then
DepartmentBuildingRoom #Status

Projected Completion

(dates may change)

ArchitectureAnderson HallStudio Rooms (13)Completed 
ArchitectureAnderson HallJury RoomCompleted 
ArchitectureAnderson HallFarrish GalleryCompleted 
ArchitectureAnderson Hall148Completed 
ArchitectureAnderson Hall153Completed 
ArchitectureAnderson Hall154Completed 
ArchitectureAnderson Hall210Completed 
ArchitectureAnderson Hall217Completed 
ArchitectureAnderson Hall230Completed 
MusicAlice Pratt Brown1401Completed 
MusicAlice Pratt Brown1402Completed 
MusicAlice Pratt Brown1403Completed 
MusicAlice Pratt Brown1404Completed 
MusicAlice Pratt Brown1131Completed 
MusicAlice Pratt Brown1133Completed 
MusicAlice Pratt Brown1705Completed 
MusicBHO/RUMPAC221Installation to begin week of 8/24/2020Completed
HumanitiesHamman HallConcourseInstallation in progressCompleted 8/24/2020
HumanitiesHamman HallAuditoriumInstallation in progressCompleted 8/24/2020
HumanitiesHamman Hall103Installation in progressCompleted 8/24/2020
HumanitiesHamman Hall106Installation in progressCompleted 8/24/2020
HumanitiesSewall Hall405Installation in progressCompleted 8/21/2020
HumanitiesSewall Hall413Installation in progressCompleted 8/24/2020
HumanitiesSewall Hall415Installation in progressCompleted 8/24/2020
HumanitiesMedia CenterTheaterCompleted 
EngineeringBRC230

Equipment/Accessories delivered

Room Completed

Remaining 8/21/2020 

EngineeringMechanical Eng. Building117AEquipment/Accessories delivered 
EngineeringMechanical Eng. Building117BEquipment/Accessories delivered 
EngineeringRyon LabOpen BayEquipment/Accessories delivered 
EngineeringRyon LabB02Equipment/Accessories delivered 
EngineeringKeck Hall108-113Completed 
EngineeringOEDK114Completed 
EngineeringOEDKLabInstallation in progressCompleted 8/24/2020
EngineeringOEDKOpen Spaces

Waiting on Customer

Carts to arrive 9/18

Completed

 

 

EngineeringOEDKB02In final testingCompleted 8/24/2020
Natural SciencesAnderson Biology123Equipment/Accessories delivered 
Natural SciencesAnderson Biology126Equipment/Accessories delivered 
Natural SciencesAnderson Biology127Equipment/Accessories delivered 
Natural SciencesAnderson Biology128Equipment/Accessories delivered 
Natural SciencesAnderson Biology129Equipment/Accessories delivered 
Natural SciencesAnderson Biology305In final testingCompleted 8/24/2020
Natural SciencesTudorS97Equipment/Accessories delivered