Department | Building | Room # | Status | Projected Completion (dates may change) | ||
---|---|---|---|---|---|---|
Architecture | Anderson Hall | Studio Rooms (13) | Awaiting Building AC Project to complete (8/12) | 8/19/2020 | Completed | |
Architecture | Anderson Hall | Jury Room | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Architecture | Anderson Hall | Farrish Gallery | Awaiting Building AC Project to complete (8/12) | 8/19/2020 | Completed | |
Architecture | Anderson Hall | 148 | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Architecture | Anderson Hall | 153 | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Architecture | Anderson Hall | 154 | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Architecture | Anderson Hall | 210 | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Architecture | Anderson Hall | 217 | Awaiting Building AC Project to complete (8/12) | 8/19/2020 | Completed | |
Architecture | Anderson Hall | 230 | Awaiting Building AC Project to complete (8/12) | Completed | 8/19/2020 | |
Music | Alice Pratt Brown | 1401 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1402 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1403 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1404 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1131 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1133 | Completed | 8/7/2020 | ||
Music | Alice Pratt Brown | 1705 | Completed | |||
Music8/7/2020 | BHO/RUMPAC | 221 | Completed | |||
Humanities | Hamman Hall | Concourse | Completed | 8/19/2020 | ||
Humanities | Hamman Hall | Auditorium | Completed | 8/19/2020 | ||
Humanities | Hamman Hall | 103 | Completed | 8/19/2020 | ||
Humanities | Hamman Hall | 106 | Completed | 8/19/2020 | ||
Humanities | Sewall Hall | 405 | Completed | 8/19/2020 | ||
Humanities | Sewall Hall | 413 | Completed | 8/19/2020 | ||
Humanities | Sewall Hall | 415 | Completed | 8/19/2020 | ||
Humanities | Media Center | Theater | Completed | 8/19/2020 | ||
Engineering | BRC | 230 | Equipment/Accessories delivered Room Completed |
Partial 8/12/2020 Remaining 8/19/2020 | ||
Engineering | Mechanical Eng. Building | 117A | Equipment/Accessories delivered | 8/12/2020 | ||
Engineering | Mechanical Eng. Building | 117B | Equipment/Accessories delivered | 8/12/2020 | ||
Engineering | Ryon Lab | Open Bay | Equipment/Accessories delivered | 8/12/2020 | ||
Engineering | Ryon Lab | B02 | Equipment/Accessories delivered | 8/12/2020 | ||
Engineering | Keck Hall | 108-113 | Completed | 8/12/2020 | ||
Engineering | OEDK | 114 | Completed | 8/19/2020 | ||
Engineering | OEDK | Lab | Completed | 8/19/2020 | ||
Engineering | OEDK | Open Spaces | Completed |
| ||
Engineering | OEDK | B02 | Completed | Partial 8/12/2020 Remaining 8/19/2020 | ||
Natural Sciences | Anderson Biology | 123 | Equipment/Accessories delivered | 8/12/2020 | ||
Natural Sciences | Anderson Biology | 126 | Equipment/Accessories delivered | 8/12/2020 | ||
Natural Sciences | Anderson Biology | 127 | Equipment/Accessories delivered | 8/12/2020 | ||
Natural Sciences | Anderson Biology | 128 | Equipment/Accessories delivered | 8/12/2020 | ||
Natural Sciences | Anderson Biology | 129 | Equipment/Accessories delivered | |||
8/12/2020 | Natural Sciences | Anderson Biology | 305 | Completed | 8/12/2020 | |
Natural Sciences | Tudor | S97 | Equipment/Accessories delivered | 8/12/2020 |