The following departmental spaces are being targeted for additional technology to enable dual teaching:
Department | Building | Room # | Status | Projected Completion (dates may change) |
---|---|---|---|---|
Architecture | Anderson Hall | Studio Rooms (13) | Awaiting Building AC Project to complete (8/12) | 8/24/2020 |
Architecture | Anderson Hall | Jury Room | Awaiting Building AC Project to complete (8/12) | 8/24/2020 |
Architecture | Anderson Hall | Farrish Gallery | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 148 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 153 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 154 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 210 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 217 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Architecture | Anderson Hall | 230 | Awaiting Building AC Project to complete (8/12) | 8/21/2020 |
Music | Alice Pratt Brown | 1401 | Completed | |
Music | Alice Pratt Brown | 1402 | Completed | |
Music | Alice Pratt Brown | 1403 | Completed | |
Music | Alice Pratt Brown | 1404 | Substantially completed | 8/14/2020 |
Music | Alice Pratt Brown | 1131 | Substantially completed | 8/14/2020 |
Music | Alice Pratt Brown | 1133 | Completed | |
Music | Alice Pratt Brown | 1705 | Completed | |
Humanities | Hamman Hall | Concourse | Installation to begin week of 8/17/2020 | 8/24/2020 |
Humanities | Hamman Hall | Auditorium | Installation in progress | 8/24/2020 |
Humanities | Hamman Hall | 103 | Installation to begin week of 8/17/2020 | 8/24/2020 |
Humanities | Hamman Hall | 106 | Installation to begin week of 8/17/2020 | 8/24/2020 |
Humanities | Sewall Hall | 405 | Installation to begin week of 8/17/2020 | 8/21/2020 |
Humanities | Sewall Hall | 413 | Installation to begin week of 8/17/2020 | 8/24/2020 |
Humanities | Sewall Hall | 415 | Installation to begin week of 8/17/2020 | 8/24/2020 |
Humanities | Media Center | Theater | Installation to begin week of 8/17/2020 | 8/21/2020 |
Engineering | BRC | 230 | Equipment/Accessories to be delivered by 8/12/2020 Installation to begin week of 8/17/2020 | Partial 8/12/2020 Remaining 8/21/2020 |
Engineering | Mechanical Eng. Building | 117A | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Engineering | Mechanical Eng. Building | 117B | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Engineering | Ryon Lab | Open Bay | Equipment/Accessories delivered | |
Engineering | Ryon Lab | B02 | Equipment/Accessories delivered | |
Engineering | Keck Hall | 108-113 | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Engineering | OEDK | 114 | Installation in progress. | 8/14/2020 |
Engineering | OEDK | Lab | Installation to begin week of 8/17/2020 | 8/24/2020 |
Engineering | OEDK | Open Spaces | Equipment/Accessories delivered Installation to begin week of 8/17/2020 | Partial Completed Remaining 8/24/2020 |
Natural Sciences | Anderson Biology | 123 | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Natural Sciences | Anderson Biology | 126 | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Natural Sciences | Anderson Biology | 127 | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Natural Sciences | Anderson Biology | 128 | Equipment/Accessories delivered | |
Natural Sciences | Anderson Biology | 129 | Equipment/Accessories delivered | |
Natural Sciences | Anderson Biology | 305 | Equipment/Accessories to be delivered by 8/12/2020 | 8/12/2020 |
Natural Sciences | Tudor | S97 | Equipment/Accessories delivered |