The following departmental spaces are being targeted for additional technology to enable dual teaching:

DepartmentBuildingRoom #Status

Projected Completion

(dates may change)

ArchitectureAnderson HallStudio Rooms (13)Installation in progress8/24/2020
ArchitectureAnderson HallJury RoomInstallation in progress8/24/2020
ArchitectureAnderson HallFarrish GalleryInstallation in progress8/21/2020
ArchitectureAnderson Hall148Installation in progress8/21/2020
ArchitectureAnderson Hall153Installation in progress8/21/2020
ArchitectureAnderson Hall154Installation in progress8/21/2020
ArchitectureAnderson Hall210Installation in progress8/21/2020
ArchitectureAnderson Hall217Installation in progress8/21/2020
ArchitectureAnderson Hall230Installation in progress8/21/2020
MusicAlice Pratt Brown1401Completed 
MusicAlice Pratt Brown1402Completed 
MusicAlice Pratt Brown1403Completed 
MusicAlice Pratt Brown1404Completed 
MusicAlice Pratt Brown1131Completed 
MusicAlice Pratt Brown1133Completed 
MusicAlice Pratt Brown1705Completed 
HumanitiesHamman HallConcourseInstallation in progress8/24/2020
HumanitiesHamman HallAuditoriumInstallation in progress8/24/2020
HumanitiesHamman Hall103Installation in progress8/24/2020
HumanitiesHamman Hall106Installation in progress8/24/2020
HumanitiesSewall Hall405Installation to begin week of 8/17/20208/21/2020
HumanitiesSewall Hall413Installation to begin week of 8/17/20208/24/2020
HumanitiesSewall Hall415Installation to begin week of 8/17/20208/24/2020
HumanitiesMedia CenterTheaterCompleted 
EngineeringBRC230

Equipment/Accessories delivered

Installation to begin week of 8/17/2020

Partial Completed

Remaining 8/21/2020

EngineeringMechanical Eng. Building117AEquipment/Accessories delivered 
EngineeringMechanical Eng. Building117BEquipment/Accessories delivered 
EngineeringRyon LabOpen BayEquipment/Accessories delivered 
EngineeringRyon LabB02Equipment/Accessories delivered 
EngineeringKeck Hall108-113Waiting on Customer 
EngineeringOEDK114Installation in progress.8/21/2020
EngineeringOEDKLabInstallation to begin week of 8/17/20208/24/2020
EngineeringOEDKOpen Spaces

Waiting on Customer

Installation to begin week of 8/17/2020

 

Remaining 8/24/2020

Natural SciencesAnderson Biology123Equipment/Accessories delivered 
Natural SciencesAnderson Biology126Equipment/Accessories delivered 
Natural SciencesAnderson Biology127Equipment/Accessories delivered 
Natural SciencesAnderson Biology128Equipment/Accessories delivered 
Natural SciencesAnderson Biology129Equipment/Accessories delivered 
Natural SciencesAnderson Biology305Installation to begin week of 8/17/20208/24/2020
Natural SciencesTudorS97Equipment/Accessories delivered 