Please see this page for some photos of the installation progress in selected rooms.

 

The following OTR rooms are targeted for additional technology to enable dual teaching: 

BuildingRoom #Room Capacity

Apprx. Social

Distance Capacity

Status

Projected Completion

(dates may change)

Anderson Bio Lab1305214Completed 
Anderson Bio Lab13112023Completed 
Anderson Hall117599Installation in Process8/21/2020
BioScience Research C2826620Completed 
BioScience Research C2845015Completed 
Brockman10114430Completed
*(Awaiting Student Mics)
 
Brockman1033012Completed 
Dell Butcher1808722Completed 
Duncan College1136024Substantially completed
Awaiting items for full completion
8/21/2020
Duncan Hall10424614Completed 
Duncan Hall10464613Completed 
Duncan Hall10647320Completed 
Duncan Hall10707320Completed 
Duncan Hall10753511Substantially completed
Awaiting replacement of a failed component.
8/21/2020
Duncan Hall1020 (Symonds II)6625Installation complete
Awaiting computer image for final testings.
8/19/2020
Herring10019742Completed 
Herman Brown Hall2274616Completed
*(Projector Control issue to be addressed 8/17/2020)
8/17/2020
Herman Brown Hall427277In Final Testing8/21/2020
Herzstein21012515Completed 
Herzstein21212315Completed 
HerzsteinAmp30040Completed 
Humanities1177021Completed 
Humanities118247Completed 
Humanities119359Completed 
Humanities

226

246Completed 
Humanities227249Installation in Process8/21/2020
Humanities327247Installation in Process8/21/2020
Humanities3283010Completed 
Keck10026548Completed 
Keck1013010Completed 
Keck1026916Installation to begin week of 8/10/2020
(Room in use by BioSchience 8/12 - 8/14).
8/19/2020
Keith Weiss Geology1006815Completed 
Keith Weiss Geology128189Completed 
Kraft Hall1054516In Final Testing8/21/2020
Kraft Hall1108624Completed 
Kraft Hall1254816Completed 
Mechanical Engineering1284814Completed 
Rayzor106288Completed 
Rayzor1132011In Final Testing8/21/2020
Rayzor1196417Completed 
Rayzor1233912Completed 
Rayzor205205In Final Testing8/14/2020
Ryon1022010Completed 
Ryon2017814Completed
*(Room is fully functional, but we discovered and
issue with the room speakers. They will be replaced week of 8/17.)
8/19/2020
Sewall30116829Substantially completed
Awaiting items for full completion
8/21/2020
Sewall3034511Completed 
Sewall3054511Completed

 

Sewall3074511Completed 
Sewall3098215Completed 
Sewall Hall207 (Symonds I)3618Completed 
Space Science1065414Completed 